Preparing Project Charters

Written by  Greg Cimmarrusti, PMP
Rate this item
(0 votes)
I come from a consulting background where you were paid proportionately to the volume of paperwork that you produced.  Half joking aside, I have produced Project Charters that were well over 30 pages in length.  This begs the question, who truly reads them and what value does it bring to the project, team members, project sponsor and the steering committee? 

When I was the PMO Director of a Fortune 500 company, I created a template for Project Charters that would produce a 2 page document (3 pages if there were a lot of signatures).  The concept was that the document truly had to mean something to all of the people involved.  It had to lay bare the scope of the project . . .


So here is the process:

After assembling the team (and preferably the project sponsor) I would attach my computer to the projector so that all could see.  I would start up my Mind Mapping software (more on that later).

It came down to a filling out a 6 step process template in order to create the Project Charter:

Project Charter Template

Project Charter Template


  • Step 1: Project Name
    • Process
    • Code Name
  • Step 2: Overall Understanding of the project

Instead of one overall Charter and individual Charters per phase, put all into one.

  • Define Phases
  • Define stages within Phases
  • Sub-projects
    • Define
    • Assign Leaders
    • May need separate Charter
    • Time Targets
    • Org Changes
    • Process Changes
    • Software tool
      • Define all Systems
      • Define all Vendors
    • Project Admin
    • Communication
      • Marketing of Project
    • Metrics
    • Rollout
      • By System
      • By Geography
  • Step 3: Objectives
    • Answer the WHY?
      • Understand Why the Company is doing the Project
    • Metrics
      • Measure

Measurability is a characteristic of the Objectives

  • Delta may need to be determined
  • Standardization
    • Ease of Use
    • Speed
    • Cost Reduction
      • Overhead reduction
    • Process
      • Refine answers
      • Increase productivity of operations
  • Step 4: Scope
    • Answer the WHAT?
      • Deliverables

Tie Scope to Deliverables

  • Step 5: Assumptions, Concerns and Constraints
    • Assumptions
    • Concerns
    • Constraints
  • Step 6: Stakeholders
    • Include people for political purposes
    • Program vs Project (or sub-project)
    • Customers
      • BU Manager
      • Division Presidents
    • Sponsors
      • Director
      • IT Working Council
    • Project Manager

Program Leaders

  • Could be Project Leader

May not do the Admin part

  • Project Analysts

To do the Admin part

  • Team Members
    • Own the task

The process at first may seem hard to follow for some of the team members, but after a while, they get it and they are enthusiastic to participate.  The mind mapping software that I use is Mindjet Mindmanager www.mindjet.com .  I will provide future articles of my use of mind mapping in project management.


I take the results of what is created and produce a 2 – 3 page document.  We all agree to the Charter, because we all had a hand in its creation.  The process takes between 1 – 3 hours depending on the participative mood of the team and the level of depth of the project scope.  Then while everyone is in the room, I get all the team members signature as well as that of the project sponsor.



Greg Cimmarrusti, PMP has over 20 years of experience providing solutions to corporations in high tech, manufacturing, real estate, entertainment, and government sectors. His background encompasses project/program management, systems analysis, implementation, and contract negotiations. Prior consulting work experience includes Hitachi Consulting, Cap Gemini Ernst & Young, and Ernst & Young. He has been the PMO Director for a Fortune 500 company.

Read 4909 times Last modified on Friday, 11 December 2009 02:41
Login to post comments

News and Promotions

Keep up to date with the latest happenings by signing up for our newsletter. Subscribe below.

Twitter Update

Who's Online

We have 738 guests and no members online

Got something to say?